Airway-Airport Loop Sewer Rehabilitation Project

Home >> Construction >> Airway-Airport Loop Sewer Rehabilitation Project

LOCATION: Main Street Pump Station, 1499 Main St., Irvine

  • What:  Rehabilitating pipelines, pumps, and valves
  • When:  Current – Spring 2025
  • Work Hours:  Day-time work, 7 a.m. – 5:30 p.m.
  • What to Expect:
    • Occasional reduced travel lanes on westbound Main St.
    • Increase in activity and noise levels

*All dates and times are subject to change due to operational factors or inclement weather.

For more project information, visit www.ocsan.gov/airwayport.

Project Description

This project will rehabilitate two parallel regional sewer pipelines, along a 1-mile stretch on Airway Avenue and Airport Loop Drive in the City of Costa Mesa, near the John Wayne Airport. The rehabilitation of the two pipelines must occur one at a time and will take place in separate phases.

Project elements also include improvements at the Main Street Pump Station.  See map below (blue line).

Project Map

Construction Schedule*

*Schedule subject to change due to operational factors or inclement weather.  

Stay In The Know

Community Liaison:
(714) 378-2965

Email:
constructionhotline@ocsan.gov

Sign up for text alerts:
click here

Related Construction

Site Location

Construction Schedule

Fall 2023 - early 2026

Construction Budget

$43.4 million