Taft Avenue Sewer Improvement

Home >> Construction >> Taft Avenue Sewer Improvement

The Taft Avenue Sewer Improvement Project remains on schedule. Crews are currently working in the median along Taft Ave. between Cambridge St. and Tustin St. As work on Taft Ave. nears completion, crews are preparing to begin the next phase in two nearby locations along the project route. To maintain progress, two crews will begin working simultaneously on Tustin St. and E. Taft Ave. in December.

Please note, no work will take place on Thursday, November 28 and Friday, November 29 in observance of Thanksgiving.

Current Work

Location: Taft Ave. from Cambridge St. to Tustin St.

  • When: Currently ongoing–End of November*
  • Hours: 8:30 a.m.—4 p.m., M–F

Construction on Taft Ave. from Cambridge St. to Tustin St.

 

 

 

 

 

 

 

 

 

 

 

 

 

Upcoming Work

Crew 1 will finish up daytime work this month and transition to night work at the Taft Ave. and Tustin St. intersection. After completing this work, they will continue north on Tustin St. towards E. Taft Ave. The work will consist of trenching, pipeline abandonment, and installation. 

  • When: Week of December 1 through January 2026*
  • Hours: Monday–Friday; 10 p.m.– 6 a.m.*

Taft Ave Sewer tustin st. map

 

Crew 2 will start near the intersection of Tustin St. and E. Taft Ave. and continue east along the median past Sacramento St. Work will begin with setting up K-rail for bypass installation and lateral relocations, then move into trenching and pipeline installation. Occasional day and night work may be needed to complete this phase of work. Additional details will be provided as this phase of work begins.

Re-striping of E. Taft Ave. between Tustin St and Sacramento St. has already taken place to prepare for the upcoming work. There are currently delineator cones in place to ensure the safety of the community. 

  • When: Week of December 1 through mid- February 2026*
  • Hours: Monday–Friday; 7 a.m.– 6 a.m.*

E. Taft Ave map

Impacts: 

  • Access for through traffic will be maintained during construction.
  • A bypass has been installed at the corner of Taft Ave. and Tustin St, which may result in intermittent crosswalk closures. Please follow all posted signs.
  • Bike lanes may be impacted during construction.
  • No street parking along the work area.
  • U-turns will not be allowed in and near the construction area during this work.
  • A four-way stop will be in place at the intersection of E. Taft Ave. and Tustin St. during a portion of the work.
  • Left turn restrictions will be in effect on E. Taft Ave.
  • Potential bus stop relocations. Visit www.octa.net for details.
  • Expect dust, noise, and increased activity near the construction zone.

 

*All dates and times are subject to change due to operational factors or inclement weather.


Project Description: 

The Taft Avenue Sewer Improvement Project will replace and relocate a portion of the Taft Sewer in the City of Orange.

This project will upsize almost two miles of pipe along Taft Avenue from Glassell Street to Sacramento Street, northbound on Sacramento Street to Brentford Avenue, to Breckenridge Street to Meats Avenue. The current pipe ranges between 12 to 15 inches and will be upsized to 18 to 21 inches.

A portion of the sewer that currently runs along Tustin Street will be relocated to North Sacramento Street where there is more room to install a larger pipe and facilitates the future maintenance of the pipeline.


Project Schedule: December 2024 – Fall 2026


Local Sewer Provider 

  • City of Orange – Water Division – (714) 288-2475

Project Location

Stay In The Know

Community Liaison:
(714) 378-2965

Email:
constructionhotline@ocsan.gov

Sign up for text alerts:
click here

Site Location

Construction Schedule

2024 - 2026

Construction Budget

$20.4 million